Designers now being accused of fraud by Liro
NY Rising’s premier construction contractor, The Liro Group, is blaming the recent design changes that weaken our homes on designers committing fraud by following the published rules for elevation. So of course, the way to fix this is to stop the recovery, require all the submitted plans to be redesigned to remove the walls, slab, flood vents and design to code minimum in the hopes that the design fee would be reduced. The plan to save money on design fees is to force designers to use an open foundation that Liro hopes will be cheaper. The open design has never been shown to be cheaper, it has no place in most of our communities and no place in 11 degree weather. If the homeowner and the designer feel that an open foundation is appropriate then they need to make that decision NOT a NY Rising contractor.
NY Rising created these rules and instead of fixing the alleged problem they make changes to design criteria that will impact the appearance, charm and character of our neighborhoods for decades to come instead of dealing with the problem head on. Once again the victim is being accused of being the problem by hiring architects that followed the published rules.
This is another case of a NY Rising failure that stops our recovery and drives families away.
Thursday, November 27, 2014
What NY Rising needs to do to fix what they broke
• Make public each HUD audit and the steps NY Rising is talking to bring the program into compliance.
• Comprehensive listing of the steps and departments each grant must pass through. Additionally, the written processes for each step of the program. Also identify each department head and their qualifications for each of the programs; reimbursement, repair, elevation, acquisition, buy out.
• Provide a timeline for grant calculation and payment. This will include a review of all submitted documentation, identification of missing, incomplete or unacceptable documentation in writing with what is required to correct it. A time frame for grant award and notification as the application leaves each step.
• For elevation applicants – written description of what the $7.80 / unit elevation price includes.
• Written description of covered items to be used in the 6100 form. At this point the program has reviewed hundreds of 6100’s and they can compile a list of items that are program allowed. And a written process for including items in the covered list.
• After a grant calculation has been made and accepted the first 50% check or make-up check should be sent no later than 1 week after the grant clarification has been signed. If you are sending the applicant a completed clarification the money needs to be available to be dispersed.
• The remaining 50% of the grant should be distributed based on a submitted plan by the homeowner and contractor that lists milestones based on inspections normally carried out during the course of construction. For example, the building department having jurisdiction over the construction may require an inspection for insulation. It may be decided that once proof of passing the insulation inspection is provided an additional 10% would be released to the homeowner. This would be used for both the repair and elevation and reconstruction program although the progress inspection may need to be modified for each program. The rules would be created with the assistance of local building departments, contractors or professional originations like NARI. The rules would be written and published.
• A comprehensive list of “close out” documentation will be provided to the grant applicant when 75% of the grant has been dispersed.
• Grant hold back amount with be 10% of total grant or $30,000 whichever is smaller. The hold back would be used to cover any duplication of benefits from ICC grants or other benefits received. The program will process the final payment within 30 days of being provided a certificate of occupancy by the building department having jurisdiction.
• Each grant applicant will be counseled on what is considered a duplication of benefits, how accidental duplication of benefits might occur and what will be done to correct DOB.
• For the reconstruction program and the $5,000 for demolition and $25,000 for extreme site conditions - the purpose of these monies will be clearly identified in writing for each applicant. For example, “$25,000 is being provided solely for the purpose of constructing a FEMA compliant foundation” If the cost of the specific item for which the money was intended for exceeds the grant other grant money may be used to supplement the cost. The intent is to allow ICC grant money to be used to the specific items of demolition and foundation construction without triggering a duplication of benefits.
• A full investigation into all thefts, destruction of office equipment, security breaches of personal information and intentional mishandling of applicant paperwork with the results to be made public corrective measures to be implemented as soon as realistically possible. Criminal charges should be sought when appropriate.
• All grant applicants should be offered credit monitoring for the duration of the NY Rising program plus one year.
• All case managers should be reviewed and evaluated every quarter. Ineffective, abusive and incompetent mangers should be removed from the program and terminated. The review would include a system of applicant reviews as well as supervisor reviews.
Obviously this is a basic list that needs some fine tuning but it is a far better plan then the mess we are dealing with now is. This proposal gives participants in the program the ability to see where they stand in the program, when they can expect awards to be given out and a way to plan for the path forward.
Tuesday, November 25, 2014
An open letter to the members of the New York State Senate
Honorable New York State Senators:
This message comes to you days before families affected by Super Storm Sandy start their third holiday season with little or no assistance from failed NY Rising Program. The disaster aid money that the State of New York has received to help Long Island rebuild from Super Storm Sandy is still tangled in red tape and effectively blocked from Long Island families by the Governor’s Office of Storm Recovery (GOSR) and NY Rising. Over two years after the storm and 20 months of New York Rising, a pitiful few cases have been closed. Much of this due to the how the program is distributing the grant awards.
The payment schedule for recipients of a NY Rising award is 50% in the beginning and 50% at completion of the project. This means that all of the physical construction must be completed as well as NY Rising mandatory inspections, NY Rising paperwork and in some cases a Certificates of Occupancy must be issued. The problem with the 50/50 award system is that once the first 50% of the grant award runs out all construction stops. Once construction stops there is no way to get the second 50% to finish the work. A Catch 22. The reality of this plan is it leaves the grant recipient to fund the second half of their grant on their own. Grant money for this exact purpose has been promised to the people of Long Island. The NY Rising program make it nearly impossible to receive the second half of the grant. If you received an email offering thousands of dollars to help rebuild your home after Sandy and all you had to do is take out a loan to get it you would delete it as spam! NY Rising has changed the rules timeless times, they have made empty promises and when questioned they blame HUD. HUD does not make the rules, they approve the rules. The GOSR & NY Rising can propose rules to HUD that streamline, not stop our recovery.
Many of you who have constituents on the coast are aware of the difficulties working with the NY Rising program, the slow turnaround time for getting funding and the devastating affect this has on our communities. But for every Sandy family waiting for money to start their reconstruction, there is a general contractor, electrician, plumber or supplier that is waiting too. NY Rising’s ridiculous 50/50 grant payout not only leaves a Sandy family to figure out how to fund the second half of their reconstruction but leaves contractors idol and out of work across the island while millions of dollars earmarked for Long Island sit in Albany.
Please help to keep Long Island’s recovery moving forward by urging the Governor’s Office of Storm Recovery to change the grant payout. The 50/50 payout plan puts families in no position to start construction and no opportunity to finish. As we enter the third holiday season since Super Storm Sandy, it’s time to bring our families home. With your help we can make effective changes and build a stronger, more resilient Long Island.
Tuesday, November 18, 2014
A simple question really
If NY Rising has been tasked with guiding our recovery from Super Storm Sandy they must have some road map that will bring us all home. So my simple question is....."What is the plan to keep construction moving when the first half of the grant runs out?" They should have a plan, it's been over 19 months since people have started being paid to help our recovery. Did this not come up?
Monday, November 17, 2014
An open letter to the New York State Assembly Men and Women of Long Island
Honorable New York State Assembly Men and Women of Long Island:
I am writing you today on behalf of my family and all of the other survivors of Super Storm Sandy that are still struggling with moving forward in our recovery. The disaster aid money that the State of New York has received to help Long Island rebuild from Supper Storm Sandy is still tangled in red tape and effectively blocked from Long Island families by the Governor’s Office of Storm Recovery (GOSR) and NY Rising. Over two years after the storm and 19 months of New York Rising, a pitiful few cases have been closed. Much of this due to the how the program is distributing the grant awards.
The payment schedule for recipients of a NY Rising award is 50% in the beginning and 50% at completion of the project. This means that all of the physical construction must be completed as well as NY Rising mandatory inspections, NY Rising paperwork and in some cases a Certificates of Occupancy must be issued. The problem with the 50% - 50% award system is that once the first 50% of the grant award runs out all construction stops. Once the construction stops there is no way to get the second 50% to finish the construction. A Catch 22. The reality of this plan is it leaves the grant recipient to fund the second half of their grant on their own. Using a Sandy damaged home as collateral to fund construction is difficult at best. Any trip around a Sandy damaged community will reveal delayed repairs, stalled construction and home sales made out of desperation. This payment schedule needs to be changed to keep the recovery moving.
Many of you who have constituents on the coast are aware of the difficulties working with the NY Rising program, the slow turnaround time for getting funding and the devastating affect this has on our communities. But for every Sandy family waiting for money to start their reconstruction, there is a general contractor, electrician or plumber that is waiting too. NY Rising’s ridiculous 50 / 50 grant payout not only leaves a Sandy family to figure out how to fund the second half of their construction but leaves contractors idol across the island while millions of dollars earmarked for Long Island sit in Albany.
Please help to keep Long Island’s recovery moving forward by urging the Governor’s Office of Storm Recovery to change the grant payout. The 50/50 payout plan puts families in no position to start construction and no opportunity to finish. As we enter the third holiday season since Super Storm Sandy, it’s time to bring our families home. With your help we can make effective changes and build a stronger, more resilient Long Island.
Thank you,
Kevin Reilly
Sunday, November 16, 2014
Sen. Charles Schumer - RE: Sandy Survivors suffering under existing NY Rising Grant payment schedule
The Honorable Charles Schumer
RE: Sandy Survivors suffering under existing NY Rising Grant payment schedule
Dear Senator Schumer:
I am writing you today on behalf of my family and all of the other survivors of Super Storm Sandy that are still struggling with moving forward in our recovery. The CDBG money that you fought so hard to get us in the days after the storm is still tangled in red tape created by the Governor’s Office of Storm Recovery (GOSR) and NY Rising. Over two years after the storm and 19 months of New York Rising, a pitiful few cases have been closed. Much of this due to the how the program is distributing the grant awards.
The payment schedule for recipients of a NY Rising award is 50% in the beginning and 50% at completion of the project. This means that all of the physical construction must be completed as well as NY Rising mandatory inspections, NY Rising paperwork and in some cases a Certificate of Occupancy must issued. The problem with the 50% - 50% award system is that once the first 50% of the grant award runs out all construction stops. Once the construction stops there is no way to get the second 50% to finish the construction. A Catch 22. The reality of this plan is it leaves the grant recipient to fund the second half of their grant on their own. Using a Sandy damaged home as collateral to fund construction is difficult at best. Any trip around a Sandy damaged community will reveal delayed repairs, stalled construction and home sales made out of desperation. This payment schedule needs to be changed to keep the recovery moving.
Recently at The 309th meeting of the members of the Housing Trust Fund Corporation, Member Marian Zucker asked James Rubin, Director, GOSR, about the recent news coverage about the GOSR. Mr. Rubin replied “the locals complaining have already received money from the State, but their complaints are based on claims of bureaucracy. He stated that these claims stem from the fact that HUD has strict requirements for the use of the money, and these requirements are passed along to the recipients.” Mr. Rubin’s comments are misleading and intended to make the hardworking people of Long Island appear to be demanding something they are not entitled to.
It is true that some money has made it into the hands of grant recipients. Typically it’s less than the plan’s promised 50% to start because the original grants are so poorly calculated each one needs to be recalculated and resubmitted back into the system for correction, creating month’s long delays in getting any starter money at all. Even once the 50% grant is corrected there is not enough money to keep the construction moving. Contracts for home construction is based on a series of progress payments, as soon as a payment is missed construction stops. The small business working to rebuild our homes can’t afford to fund these projects while the homeowner waits for the second 50%.
Right now NY Rising’s only answer to the families is the incredibly restrictive CDCLI bridge loan. Which only kicks in after the first 50% of the money is spent. Again asking families to fund their grant awards by using loans instead of what the CDBG grant money is intended for. Clearly having the GOSR tell grant recipients that they need to take out a loan to get the last 50% of a grant that they are entitled to shows how totally unrealistic the payment scheme is. When we appeal to people like Mr. Rubin, we get the common excuse from the GOSR of “it’s not us it’s HUD”. If that is the case why is New Jersey’s program, funded the same way, receiving 50%, 25% and 25% at the end?
I am asking for your help in getting this money into the hands of the people who are desperate to get on with their lives. This payment arrangement needs to be corrected in a way that fairly addresses the homeowner’s needs while protecting the State. Asking Sandy victims to somehow fund their own grants is unfair and unworkable for many.
Kevin Reilly
Long Beach, New York
Sunday, November 9, 2014
The real reason for the 50% hold back, insight from the minutes of the 309th meeting of the members of the Housing Trust Fund Corporation October 16th 2014
NY Rising says they have no control over how HUD allows them to distribute grant money. 50% upfront and 50% at the back end. You have heard me say over and over that this is creating financial stress on families involved in the NY Rising program. We have been told there is nothing that can be done about it. Well I think that there is a little deception by NY Rising as to the real reason that homeowners are being forced to fund the second half of their grant awards. Take this exchange between Mr. Galloway (Director of Operations, Governor’s Office of Storm Recovery,), Mr. Houghton (Chief Executive Officer Housing Trust Fund Corporation) and Ms. Bova-Hiatt (General Counsel, Governor’s Office of Storm Recovery) taken from the minutes of the 309th meeting of the members of the Housing Trust Fund Corporation October 16th 2014
“Mr. Galloway stated that basic duplications will occur. He stated that each agreement with the homeowner has subrogation language requiring additional funds to be returned and disclosed.
Mr. Houghton asked about the mechanism to ensure the return of money.
Ms. Bova-Hiatt stated that homeowners receive 50% up front and 50% on the back end, and during the time their homes are under construction, money received gets taken off the back end. GOSR reaches out to FEMA and insurance again to make sure nothing else was paid out.”
Read that again. “during the time their homes are under construction, money received gets taken off the back end”
I interpret this to mean that NYR is holding back the 50% until the end NOT because HUD said so but rather they are using the last 50% it as collateral against a possible DOB. Basically making you find some way of paying for the second half of the construction yourself and then picking over what’s left looking to recapture as much as possible. They are holding that last 50% of your grant award in reserve because if you receive money to finish the construction from another source then they can just reduce the last payment by that much.
On the surface I understand what they trying to do. If NYR holds 50% of the grant money in reserve, any duplication of benefit that comes up can be handled by just reducing the final payment. The problem at this stage of the recovery is NYR still has no clear understanding of what was paid by flood and homeowners insurance, they have no understanding that there is very little help coming from other grant sources at this time and any additional money from insurance and FEMA payments is likely to be small in comparison to half of the grant. Holding half of the grant until the end to use as duplication of benefits collateral is catastrophic for families trying to rebuild.
It is clear that after 17 months the program still has no real concept of what the people who are rebuilding are dealing with. NY Rising needs to make sure that this precious grant money is used as it was intended – to rebuild Sandy damaged homes. On Long Island, construction project have a serious of payments that are made along the way not one in the beginning and one at the end. In the real world if you can’t make a payment, construction stops. That is what is happening because NY Rising is holding half of the grant. I would like someone from the Governor’s Office of Storm Recovery to explain exactly where the second half of the construction money is supposed to come from. Do they expect contractors to wait for tens of thousands of dollars from hundreds of families? Are there other grants that we need to apply to? Are these mythical bridge loans that we hear about going to be treated as a DOB? There seems to be a good plan in place to keep the money out of the hands of Long Island families to prevent a possible duplication of benefits but is there a plan to keep the construction moving? I don’t think so. And that needs to change.
If you would like to view the whole document you can find it here: